On behalf of the precast concrete plant in Linkenheim, Martin Dobler Projektmanagement GmbH successfully carried out the planning, tendering, and implementation of a new mixing plant, including heating and concrete recycling facilities. Our tasks included developing the concept for the mixing plant, tailored to the specific requirements of precast concrete production, as well as conducting a detailed tendering process.
We conducted a comprehensive comparison of offers to ensure an optimal price-performance ratio for our client. We also provided advisory support to the client during the negotiation phases and the award decision. In addition, our company was responsible for drafting the factory contract and accompanied the acceptance process to ensure compliance with the agreed specifications.
Our involvement in this project demonstrates our commitment to realizing efficient solutions that meet the requirements of precast concrete production.
Scope of services:
- Planning of a new mixing plant for the precast concrete plant in Linkenheim, including heating and concrete recycling facilities.
- Tendering of the required works and systems.
- Creation of a comparative analysis of bids to evaluate the received offers.
- Advising the client during negotiations with suppliers and supporting the award decision.
- Drafting the factory contract for the implementation of the mixing plant.
- Supervision of the acceptance of the installed plant to ensure compliance with all agreed specifications.